Plan ahead
Planning for Your Garage
Review permitting, engineered drawings, utility locations, and site preparation before ordering or installing your building.
Generic Engineered Drawings
Generic drawings are free for buildings under 30 feet wide. These are drawings stamped by an engineer and may be used for permitting when required.
Not every location requires engineered drawings, and some locations do not require a building permit at all. Requirements vary. It is the homeowner's responsibility to check with the local building or permitting office and find out what is required for their property.
Site-Specific Engineered Drawings
Buildings 40 feet wide or larger may sometimes require site-specific drawings. These are more detailed, project-specific engineered drawings and typically cost around $0.50 per square foot.
To request either generic or site-specific drawings, an order must first be entered into the system. An engineering company then prepares the drawings and sends them to you.
Check for Underground Water Lines
Before concrete work or placing a building on gravel, make sure you know where underground water lines are located. Our buildings use long anchors, which can reach deep into the ground and may hit a buried water line.
If you are unsure where utilities are located, call 811 before digging or installing anchors to have underground utility lines marked.
Ground Level and Concrete Slab
For a carport installation, the ground should be within 4 inches of level across the installation area.
If you are installing on a concrete slab, make sure the slab is built to the exact dimensions required for the building. The slab and surrounding grade should allow water to drain away from the building rather than toward it.